Weaver Park Pier Updates
The City of Dunedin has done extensive research on the best way to proceed with the permitting process
Pre-application meeting to be scheduled with U.S. Army Corps of Engineers to determine permitting process
The City is looking at replacing the decking and the railings and not the pilings so it can be permitted as a repair
Permitting Options
- If the pilings don’t have to be replaced, this has the potential to expedite the permitting timeline
- If piling replacement is necessary, Weaver Park Pier project will need to undergo the full permitting process